The City of Madison and Simple Mining LLC are moving forward with plans for a digital currency mining facility following approval of land lease and electric service agreements October 5th.
The proposed 10-megawatt facility would sit on about 3.75 acres of city-owned property at 840 Southeast 10th Street near the Southeast Substation.
Simple Mining must now obtain a building permit before construction can begin.
The facility will operate under the city’s Large Load Electric Rate and Heartland Energy’s Interruptible Load Program, requiring it to reduce or suspend electricity use during emergencies or high demand.
City Administrator Jameson Berreth says revenue from Simple Mining will remain in the city’s Electric Fund.
Utilities Director Mike Plooster says Simple Mining will also cover costs associated with providing electric service and any necessary system improvements.
Construction has been estimated to take about three months once underway, with the timeline depending on remaining permitting and development steps.